Antrim Area Hospital is an acute trust of 350 beds in Northern Ireland. It has installed the largest wind turbine at any UK hospital and is on track to save £90,000 a year in energy costs.

Additional images

case study image

Click to see a slideshow of these images

Overview

Antrim Area Hospital is an acute trust of 350 beds and is part of Antrim United Hospitals Trust. Spurred on by the public sector building energy reduction target, the Hospital investigated installing a wind turbine on site to provide energy.

Following a feasibility study, a wind study and an environmental impact assessment (EIA), planning permission for the project was given. From idea conception to installation took 3 years. The civil work started in autumn 2004 and the turbine was delivered in January 2005.

It took only three days to install and has been fully operational since 7th February 2005. The 40 metre high 660 kW Vestas V47 wind turbine is the largest at any hospital in the UK. It will generate an average of 1.2 million units of electricity per annum, which is used as base load replacement. It has the potential to provide enough electricity for the hospital during the night, and two-thirds of the power needed during the day, which would otherwise cost £90,000 a year. Even in low wind conditions the turbine is cost effective and the money that would have been spent on power is freed up for improved services for patients.

The turbine cost £497,000, of which 80% was a grant from the Government Central Energy Efficiency Fund. Without a grant it would take five years for the initial cost to be repaid (at 2005 energy prices).

The wind turbine has been a success and other hospitals across the UK are taking an interest in replicating what has been achieved at Antrim.

Benefits As well as cutting Antrim Area Hospital’s energy bill, the project has also reaped the following benefits:

• Reduces power generation waste
• Benefits air pollution and climate change
• No impact on biodiversity
• Easy to return the site to how it was before.

Key features

energy
health

Key data

Completion Date: 05/02/2005
Project Team: Consulting Engineers: White Young Green; Contractors: Total Communications Infrastructure (TCI)
Cost: £497,000
Local Authority: Antrim

Links

Antrim Area Hospitals
White Young Green
Total Communications Infrastructure

Back to Case studies


Rate this case study

How useful was this case study to you?
(0 = lowest and 5 = highest)

012345

Review

Your rating and comment will be displayed anonymously. Terms and conditions